Turner County Bridge


Turner County Bridge

The project consisted of the removal of a 160’ 5 span steel girder bridge and building a new 192’ 3 span concrete girder bridge. This work consisted of 2 piers that required cofferdam work and building 32’ long stem wall and a cap in each cofferdam, 2 abutments, placing the concrete girders, pouring an 8” thick concrete deck, jersey barriers, approaches, sleepers, rip rap, grading and asphalt paving.

Details

Vertical

  • Heavy/Highway and Civil

Division

  • SFC Civil Constructors

Status

  • In Progress

Client

  • SDDOT

Location

  • Turner County, SD